Thursday, July 31, 2008

Update

After weeks of not really noticing much change at the sight, things have taken a huge turn. The 5 people that would normally be there have multiplied to about 15. They are now working 12 hour days and changes are beginning to happen on a daily basis.
I walked into the spot tonight and saw a restaurant!! The kitchen is about 95% complete, Matt and I will begin the process of multiple cleanings to get the kitchen ready for inspection. The FOH has the gorgeous crown molding and decorative beams running through it, and most important the toilets are in!!!!!!!
This week water, electricity and gas will be on.....Pictures will soon follow.